Costing a RAP: why resettlement budgets are wrong before they are approved
What a resettlement budget must contain, the line items projects systematically omit, and why contingency is not padding.
Resettlement budgets are typically wrong in one direction. They are built from an asset inventory, priced at statutory rates, and approved before anyone has tested whether those rates reach replacement cost or counted the people who will be added to the register later. The overrun that follows is then treated as a surprise, when it was a structural feature of how the number was produced.
This matters beyond accounting. An under-budgeted RAP does not fail quietly — it fails as delayed payments, which under both standards means displacement occurring before compensation.[1]
What the budget has to cover
Compensation for land and assets is the visible line and rarely the largest share of total cost. A complete resettlement budget covers:
- Compensation — land, structures, crops, trees, ancillary assets, at replacement cost rather than statutory rate.
- Resettlement assistance — moving costs, transitional allowances, tenure regularisation at the replacement site.
- Replacement site development — land purchase, servicing, access roads, water, sanitation, and any social infrastructure the plan commits to.
- Livelihood restoration programmes, which run for years after the last payment.
- Vulnerable household assistance above the standard entitlement.
- Implementation capacity — the resettlement unit, enumerators, valuers, community liaison officers, transport, systems.
- The grievance mechanism, staffed and running for the duration.
- Monitoring, evaluation and the completion audit, including the external auditor.
- Contingency, sized against identified risks rather than as a flat percentage.
The items that get omitted
Everyone added after the census
Registers grow. Grievances are upheld, people missed at enumeration are added, tenants and business employees surface once implementation begins and the mechanism starts working. A budget built on the census count with no allowance for register growth is budgeting for the population that was found, not the population that is eligible.[3]
The gap between statutory rates and replacement cost
Where gazetted rates sit below replacement cost, the project must top them up. If the budget was priced at the gazetted rate, that top-up is unfunded — and it is not a marginal figure. It is frequently the single largest variance in the whole budget, and it is entirely predictable at planning stage by testing the rates.
Time
Resettlement runs for years, in economies where construction materials and land prices move quickly. A valuation done in year one and paid in year three has not delivered replacement cost — it has delivered a three-year-old number. Budgets need an escalation mechanism and a rule for revaluation after a defined period, or they systematically under-deliver the longer implementation takes.
Livelihood restoration, properly costed
Livelihood programmes are frequently entered as a token line because their design is not finalised at budget stage. They are the longest-running commitment in the plan and the one most likely to require extension when monitoring shows incomplete recovery.[3] A placeholder here is a decision to underfund the requirement that determines whether the resettlement succeeded.
The cost of proving it happened
Systems, record-keeping, reconciliation and audit preparation are real costs and almost never separately budgeted. They are then absorbed by staff who were funded to do something else, which is the practical reason documentation degrades under schedule pressure.
A budget that funds paying compensation but not evidencing it has funded half the requirement, and it is the half that gets tested.
Contingency is not padding
A flat ten percent contingency is a convention, not an estimate. Useful contingency is sized against identified risks: rate revisions, register growth, schedule slip and revaluation, land price movement at the replacement site, and livelihood programme extension.
Naming each risk changes the conversation with the approving authority. A finance director can reject "contingency". Rejecting "the funds required if the gazetted crop rate is confirmed to be below replacement cost" requires them to take a position on a specific, documented exposure.
Who pays, and when
In donor-financed infrastructure the resettlement cost is typically borne by the government implementing agency, while the works are financed by the lender. That split has a practical consequence: resettlement funds move on a national budget cycle, and construction moves on a disbursement schedule. When those two calendars diverge, compensation is late and works are on time — which is precisely the failure mode both standards exist to prevent.[2]
The mitigation is unglamorous: front-load the resettlement budget so funds are available before the works programme needs the land, and treat compensation completion as a gating condition on mobilisation rather than a parallel activity. Every project that has had contractors waiting on unpaid households learned this the expensive way.
Sources
- [1]Performance Standard 5: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2012.
- [2]ESF Guidance Note 5: Land Acquisition, Restrictions on Land Use and Involuntary Resettlement — World Bank, 2018.
- [3]Good Practice Handbook: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2023.
- [4]Guidance Note 5: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2012.
Olule Solomon
Lead Consultant, ValueSpace
Olule Solomon is Lead Consultant at ValueSpace, where he works on land acquisition and resettlement systems for donor-financed infrastructure in East Africa. He writes about the practical gap between what the safeguard standards require and what a project can actually evidence at completion audit.
Related reading
- Full replacement cost: the valuation rule projects get wrong most oftenWhat replacement cost means under PS-5 and ESS-5, why depreciation cannot be deducted, and how to evidence the basis.
- Reconciling compensation payments: the evidence gap nobody budgets forPaying compensation and proving you paid it are different problems. How disbursement files are reconciled back to entitlements.
- What is a Resettlement Action Plan? A practitioner's guideWhat a RAP is, when a lender requires one, what it must contain, and why most are judged on evidence rather than intent.
Free entitlement matrix template
15 loss categories, eligibility split by tenure, valuation basis and the PS-5 provision behind every row. CSV, no registration wall.
Get the template →The software behind this
SmartLARMS keeps the record this article describes
PAP register, replacement-cost valuations, entitlements, recorded payments reconciled against disbursement files, and grievances — every change attributed and time-stamped, so a completion audit is evidenced rather than reconstructed. Offline-first in the field.