Temporary land take: camps, borrow pits, access roads and reinstatement
Temporary occupation is treated as a contractor matter and generates permanent losses. What to require and who pays for it.
Construction needs land the permanent works do not occupy: camps, laydown areas, borrow pits, haul roads, diversions, spoil disposal. It is usually taken by the contractor, by private arrangement with the occupier, after the RAP is approved and without reference to it.
That arrangement is the source of a recurring category of harm — land occupied for three years and returned unusable, crops destroyed with no record, payments agreed verbally with whoever appeared to be in charge — and it is entirely foreseeable at planning.
Temporary is a description of intent, not of effect
Temporary occupation still causes economic displacement for its duration, and where the duration is several agricultural seasons the effect on a household is not distinguishable from permanent loss. The standards do not carve out temporary acquisition: the test is whether people lose land, assets or access to income, not whether the loss is permanent.[1]
Some temporary takes are permanent in substance. A borrow pit is a hole; topsoil stripped and mixed with subsoil does not recover its productivity for years; compaction under a haul road persists. Reinstatement to the original condition is frequently not achievable, and where it is not, the difference is a permanent loss that should have been compensated as one.
If the land will not return to its former productive capacity within a season or two, the take is not temporary in any sense the occupier would recognise.
Bring it inside the instrument
The practical remedy is to treat temporary land requirements as part of the resettlement instrument rather than as a construction matter:
- Entitlement rows for temporary occupation — annual payment for the occupation period, compensation for crops and trees destroyed, compensation for any residual loss of productivity after reinstatement, and access arrangements where a holding is severed.[2]
- A reinstatement specification in the works contract: topsoil stripped and stockpiled separately, depth of decompaction, drainage, agreed condition on handback.
- A condition survey before occupation, photographed and signed by the occupier, which is the only basis on which reinstatement can later be assessed.
- The same grievance mechanism as the main programme, so that contractor-caused impacts do not sit outside the record.
The contractor arrangement problem
Where a contractor negotiates directly, three things follow predictably. Rates diverge from the project's own compensation schedule, usually downward, and the inconsistency becomes a grievance from households who were paid properly nearby. Agreements are made with the person present rather than the person entitled — commonly the landholder rather than the cultivator. And no record reaches the project, so at completion audit the project cannot say who was affected by its own construction.
The mitigation is contractual and cheap: require the contractor to use the project's rates and forms, to route every agreement through the resettlement unit for verification against the register, and to obtain condition surveys before occupation. Make the reinstatement certificate a condition of final payment.[3]
Where camps and quarries create their own displacement
A construction camp is a settlement. It brings workers, in-migration, demand for housing and services, and its own footprint of acquired land. A quarry brings blasting, dust and heavy traffic through communities that are not otherwise affected by the project at all.
These sites are frequently selected after the plan is approved, which means the population around them was never surveyed, never consulted and has no baseline. Where site selection cannot be completed in time for the main instrument, the instrument should at least fix the process: screening criteria, a requirement for enumeration before occupation, and the entitlement framework that will apply.[4]
Handback
Reinstatement fails at the end of a contract, when the contractor is demobilising and the incentive to complete it is at its weakest. Three provisions hold the line: a retention released only on certified reinstatement, a joint handback inspection with the occupier present and signing, and a defined period afterwards during which residual productivity loss can still be claimed.
Without the third, an occupier who accepts handback in good faith and discovers over the following season that the land yields half of what it did has no route back to anyone.
Sources
- [1]Performance Standard 5: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2012.
- [2]Guidance Note 5: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2012.
- [3]Good Practice Handbook: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2023.
- [4]ESF Guidance Note 5: Land Acquisition, Restrictions on Land Use and Involuntary Resettlement — World Bank, 2018.
Olule Solomon
Lead Consultant, ValueSpace
Olule Solomon is Lead Consultant at ValueSpace, where he works on land acquisition and resettlement systems for donor-financed infrastructure in East Africa. He writes about the practical gap between what the safeguard standards require and what a project can actually evidence at completion audit.
Related reading
- Resettlement on linear projects: transmission lines, roads and pipelinesLinear projects displace thousands economically and few physically. Why that inverts almost every assumption in a standard RAP.
- Economic displacement of informal traders, kiosks and roadside businessesLosing a stall is losing a location, not a structure. Why disturbance allowances under-compensate the most exposed businesses.
- Designing a grievance redress mechanism that a lender will acceptWhy resettlement generates the most complaints of any safeguard issue, and what separates a working GRM from a logbook.
Free entitlement matrix template
15 loss categories, eligibility split by tenure, valuation basis and the PS-5 provision behind every row. CSV, no registration wall.
Get the template →The software behind this
SmartLARMS keeps the record this article describes
PAP register, replacement-cost valuations, entitlements, recorded payments reconciled against disbursement files, and grievances — every change attributed and time-stamped, so a completion audit is evidenced rather than reconstructed. Offline-first in the field.