The valuation report: approval, statutory process and the delay it creates
Between an assessed value and an authorised payment sits a statutory approval chain. Where it stalls and what shortens it.
Between an assessed value and money in a household's hands sits an approval chain that nobody plots until it starts failing. On most public projects it has four or five steps, each with its own queue, and together they account for more of the delay between valuation and payment than any dispute does.
The chain, in the order it usually runs
- Field assessment by the valuation team, working from the asset inventory.
- Internal review within the consultancy or the agency, checking arithmetic, rates and completeness.
- Statutory or government valuer approval, where national practice requires a state valuation function to endorse the figures.
- Authorisation of the award by whoever holds the delegation, which is often tiered by amount.
- Funds release through the finance function, subject to appropriation and cash availability.
Every step is reasonable in isolation. Together they can take a year, and the plan usually shows them as a single bar labelled valuation.
Why approval stalls
The recurring causes are mundane and therefore fixable. Files submitted incomplete and returned. Rates used that the approving authority does not accept, discovered only at submission. Batch sizes too large to review, so nothing clears. Delegation thresholds that route ordinary cases to a committee meeting monthly. Staff turnover in the approving office, with the successor asking the questions the predecessor had already settled.
The measure that helps most is agreeing the methodology with the approving authority before assessment begins rather than submitting and defending afterwards.[2] A rate basis that the approver has already accepted converts approval from an argument into a check.
Submit the method first, the numbers second. An approver seeing both at once will interrogate both at once.
What the report has to carry
A valuation report that will be read years later by a completion auditor needs more than a schedule of amounts. It needs the date of assessment, the basis for each category, the source of every rate and how it was derived, the replacement-cost benchmark and any top-up applied, the assumptions made, and the identity and qualification of the valuer.[1]
Where a statutory schedule was used, the report should show the comparison against replacement cost rather than leaving a reviewer to discover a shortfall by doing the arithmetic themselves.[3]
Batching and the payment queue
Approval is faster in small consistent batches than in large mixed ones, and the batching decision has fairness consequences: whoever is in batch one is paid a year before whoever is in batch six, for the same loss.
Two rules make that defensible. Batch by geography aligned to construction sequence, so payment order tracks when possession is actually needed. And prioritise vulnerable households within every batch, since delay falls hardest on households with no reserves.
Refreshing a stale valuation
A valuation is a statement about value at a date. Where approval and funding take two years, the assessed amount is no longer replacement cost, and paying it in full still leaves the household short.
Provide for it in the plan: a revaluation trigger where payment has not occurred within a defined period, or indexation against a published index in the interim. Both cost money and both are cheaper than a completion audit finding that compensation was inadequate at the date it was paid.[4]
What to do during preparation
- Map the approval chain end to end, naming each step's owner and typical duration.
- Trace one real payment through it before the plan is finalised.
- Agree valuation methodology with the approving authority in advance.
- Build the resulting durations into the schedule instead of an optimistic single bar.
Sources
- [1]Performance Standard 5: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2012.
- [2]Guidance Note 5: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2012.
- [3]Good Practice Handbook: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2023.
- [4]Compulsory Land Acquisition in Uganda (Policy Briefing Paper 47) — Advocates Coalition for Development and Environment (ACODE), 2020.
Olule Solomon
Lead Consultant, ValueSpace
Olule Solomon is Lead Consultant at ValueSpace, where he works on land acquisition and resettlement systems for donor-financed infrastructure in East Africa. He writes about the practical gap between what the safeguard standards require and what a project can actually evidence at completion audit.
Related reading
- Sequencing RAP implementation: payment, possession and handoverCompensation before displacement is a rule with a specific order behind it. Where schedules break, and what breaks with them.
- Interest on delayed compensation: the entitlement nobody claimsMost acquisition statutes provide for interest on late payment. Almost no displaced household knows it, and few projects volunteer it.
- Valuation disputes: objection, appeal and the case for settling earlyA contested valuation has three possible routes and one predictable outcome. Which disputes to settle, and which have to go the distance.
Free entitlement matrix template
15 loss categories, eligibility split by tenure, valuation basis and the PS-5 provision behind every row. CSV, no registration wall.
Get the template →The software behind this
SmartLARMS keeps the record this article describes
PAP register, replacement-cost valuations, entitlements, recorded payments reconciled against disbursement files, and grievances — every change attributed and time-stamped, so a completion audit is evidenced rather than reconstructed. Offline-first in the field.