Delay, inflation and the erosion of compensation between valuation and payment

Olule Solomon11 min read

Abstract

Replacement cost is assessed at a point in time and paid at another, and the interval between the two is frequently measured in years. Over that interval prices move, the local land market repositions in anticipation of the acquisition, and the sum that would have purchased an equivalent asset at valuation no longer does. This paper treats payment delay as a substantive compliance issue rather than an administrative one, examines the mechanisms through which delay erodes the adequacy of compensation, and considers the instruments available to preserve it — indexation, revaluation triggers and interest — along with why they are so seldom used.

Replacement costPayment delayCompensation adequacyInflationInvoluntary resettlement

1. The requirement and the interval

The standards are consistent that compensation must be at full replacement cost and, in the ordinary case, paid before possession is taken. Both halves of that requirement are stated together for a reason: replacement cost is a statement about what a sum will buy, and it is only true at a date. Detached from prompt payment it degrades into a historic figure.

Actual intervals are long. Valuation is completed during RAP preparation; the plan is reviewed and disclosed; approvals are obtained, sometimes from a statutory valuation authority with its own queue; funds are appropriated within an annual budget cycle; disputes over identity, boundaries or succession are resolved individually. Two years from valuation date to payment is unremarkable, and considerably longer intervals occur where litigation or funding interruption intervenes.

2. Three distinct erosion mechanisms

General inflation is the most obvious and the least interesting analytically, since it is measurable and correctable if anyone chooses to correct it. Its effect on adequacy is nonetheless material at double-digit rates over multi-year intervals.

Sector-specific movement is more damaging because it is faster than general inflation and specific to the assets being replaced. Construction materials and skilled building labour rise sharply where a large project is under construction in the same district, which is exactly where displaced households are trying to rebuild. Compensation calculated against pre-project material rates, paid during the construction peak, buys a materially smaller house.

Local land price movement is the third and is partly caused by the acquisition itself. Once an alignment is known, land in the surrounding area reprices upward in anticipation, and the compensated household is buying replacement land in a market that has already adjusted to the money about to enter it. This is not speculation in the pejorative sense; it is the market processing information.

3. Why the erosion is rarely visible

Monitoring records payments made against entitlements assessed, and both figures are nominal. A programme that pays every household the assessed amount reports full compliance, and by the arithmetic it applies, that is correct. The question of whether the amount still corresponds to replacement cost at the date of payment is not asked because no indicator poses it.

The check is not difficult. It requires the valuation date and the payment date on each record, which any competent register holds, and a repricing of a small basket of representative replacement assets at the payment date. The ratio of the two is a direct measure of compensation adequacy over time and would be one of the more informative indicators in a monitoring framework. Its absence is a design omission rather than a data constraint.

4. The available instruments

Indexation adjusts the assessed sum by a published price index between valuation and payment. It is administratively simple, uses an external and non-negotiable reference, and captures general inflation while under-correcting for sector-specific and local land movement.

A revaluation trigger provides that where payment has not occurred within a defined period — twelve months is the usual formulation — the valuation is refreshed. It is the more accurate instrument and the more expensive, and it creates an incentive the project may find uncomfortable, since delay then has a cost borne by the project rather than by the household.

Interest on delayed compensation exists in several national legal frameworks, including where a statutory rate attaches to sums outstanding after possession. Where it exists it is frequently unclaimed, because claiming it requires knowledge and standing that displaced households seldom have.

The reason none of these is standard is that each converts an invisible transfer from households to the project into a visible line in the budget. The transfer occurs either way; the instruments only determine who bears it and whether anyone can see it.

5. Sequencing as the first-order remedy

The financial instruments treat the symptom. The structural remedy is to compress the interval, and most of the interval is created by decisions taken long before valuation: procuring the RAP in parallel with a footprint that is not yet fixed, so that valuation precedes the design freeze and must later be redone; committing to payment on an annual appropriation cycle without securing the appropriation; and beginning the identity and succession work that resolves individual disputes only after payment has been authorised, when it could have begun at census.

Of these the last is the most tractable. A significant share of long-delayed payments concerns claims that were unresolved at census — a deceased registered owner, a boundary in dispute, a claimant without documentation — and were carried forward rather than worked. Identifying that subset at enumeration and starting the resolution process immediately shortens the tail substantially, and the tail is where the erosion is largest.

6. Conclusion

Delay is treated as a scheduling problem and is in substance a valuation problem. A programme that pays assessed amounts late has not paid replacement cost, whatever its disbursement records show, and the shortfall is borne entirely by the displaced household. Making it visible requires only that the monitoring framework compare the assessed sum to the cost of the asset at the date the money arrived — which is the comparison the standard's own definition implies and almost no project performs.

References

  1. [1]Performance Standard 5: Land Acquisition and Involuntary Resettlement. International Finance Corporation, 2012.
  2. [2]Guidance Note 5: Land Acquisition and Involuntary Resettlement. International Finance Corporation, 2012.
  3. [3]ESF Guidance Note 5: Land Acquisition, Restrictions on Land Use and Involuntary Resettlement. World Bank, 2018.
  4. [4]Good Practice Handbook: Land Acquisition and Involuntary Resettlement. International Finance Corporation, 2023.
  5. [5]Compulsory Land Acquisition in Uganda (Policy Briefing Paper 47). Advocates Coalition for Development and Environment (ACODE), 2020.