Putting resettlement obligations where the contractor will actually see them

Most land-related harm during construction is caused by a contractor bound by a contract that never mentioned the RAP.

Olule Solomon9 min read

Most land-related harm during construction is caused by a contractor operating under a contract that never mentions the resettlement plan. The plan sits with the client's safeguards unit; the contractor works to drawings, a programme and a bill of quantities. Between those two documents is where the damage happens.

What contractors do that generates claims

  • Occupying land outside the corridor for laydown, spoil, access or turning.
  • Negotiating privately with occupiers at rates below the project's own schedule.
  • Destroying crops, walls, water connections and access without recording any of it.
  • Selecting camps, quarries and borrow pits on land that was never surveyed.
  • Blocking access to homes and businesses for months.
  • Reinstating temporary land to a standard that leaves it less productive.
  • Bringing a workforce with cash into a community with none.

Each of these is foreseeable, and each is cheaper to prevent through a contract clause than to remedy through a grievance process.[1]

A contractor will do what the contract measures and pays for. If land impacts are not in the contract, they are not in the contractor's programme either.

Clauses that earn their place

  1. No entry onto land outside the released corridor without written clearance from the resettlement unit. This single provision prevents most of the list above.
  2. All land arrangements routed through the project, using the project's rates and forms, with every agreement recorded in the project register.[2]
  3. Condition surveys before occupation, photographed and signed by the occupier, as a condition precedent to entry.
  4. Reinstatement specification — topsoil stripped and stockpiled separately, decompaction depth, drainage, agreed handback condition — with retention released only on certified reinstatement.
  5. Camp, quarry and borrow pit sites subject to screening and approval, with enumeration completed before occupation.
  6. Access maintenance to homes and businesses, specified and measured rather than left to good practice.
  7. Worker code of conduct, signed individually, with defined consequences and a reporting route independent of site management.[3]
  8. Grievances routed to the project mechanism, with a contractual response time and reporting obligation.

Make it measurable and payable

Obligations with no price attached get deferred. Reinstatement, access maintenance, condition surveys and community liaison should appear as items in the bill of quantities or as a defined lump sum with milestones, so that the contractor is paid for doing them and visibly not paid for not doing them.

Where these sit only in a specification clause, they compete with the programme and lose.

Supervision has to include the social side

The supervision consultant certifies payment, which makes it the effective enforcement point. If its team is entirely engineering, nobody with authority to withhold a certificate is looking at land occupation, reinstatement or community liaison.[4]

A social specialist within the supervision team, with a defined role in certification, is what converts these clauses from text into practice.

Before mobilisation

  • Brief the contractor's management on the RAP itself, not just on the ESHS annex.
  • Walk the corridor jointly to establish what has been released and what has not.
  • Agree the rate schedule for minor damage and the settlement threshold.
  • Establish the grievance interface and the reporting format on day one.
  • Confirm condition surveys are complete for every area to be occupied.

Sources

  1. [1]Performance Standard 5: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2012.
  2. [2]Good Practice Handbook: Land Acquisition and Involuntary Resettlement — International Finance Corporation, 2023.
  3. [3]ESF Guidance Note 5: Land Acquisition, Restrictions on Land Use and Involuntary Resettlement — World Bank, 2018.
  4. [4]The Equator Principles (EP4) — Equator Principles Association, 2020.

Olule Solomon

Lead Consultant, ValueSpace

Olule Solomon is Lead Consultant at ValueSpace, where he works on land acquisition and resettlement systems for donor-financed infrastructure in East Africa. He writes about the practical gap between what the safeguard standards require and what a project can actually evidence at completion audit.

Related reading

Free entitlement matrix template

15 loss categories, eligibility split by tenure, valuation basis and the PS-5 provision behind every row. CSV, no registration wall.

Get the template →

The software behind this

SmartLARMS keeps the record this article describes

PAP register, replacement-cost valuations, entitlements, recorded payments reconciled against disbursement files, and grievances — every change attributed and time-stamped, so a completion audit is evidenced rather than reconstructed. Offline-first in the field.